Beneficiary: SCHNEIDER ELECTRIC ROMANIA S.R.L., Bucharest - Period: 2014-2017
Within this project, the following types of works were executed:
  • modernization of three average voltage electric stations 6kV inside the bearing factory Koyo Romania Alexandria S.A. by replacing the old cells, type Bailesti (75 pieces) with cutting-edge cells, type MCSet 6kV (65 pieces) with vacuum sealed switches manufactured by Schneider Electric;
  • the 6kW power cables from the SRA electric station to substations SC1, SC2, SC3 were replaced. The total length of these electric power cables was above 30 km and they were installed on metal chutes type OBO into underground electric channels and onto newly constructed stockades.
  • A fibre optic system was installed between the electric stations modernized for the supervision and control of the new equipment (cells) installed into the 3 electric stations with a central dispatcher in the SRA 6kV Koyo Alexandria station.